LONDIANI DAM CONSTRUCTION 2026: EXCAVATION AND EARTHWORKS SCOPE
INSIDE KERICHO COUNTY'S FLAGSHIP WATER PROJECT — FROM DAM EMBANKMENT TO TRANSMISSION PIPELINES
PROJECT OVERVIEW: WHAT IS LONDIANI DAM?
Londiani Dam is a proposed multi-purpose water storage and supply project in Kericho County, Kenya. Situated near Londiani town in the Kipkelion East Constituency, the dam will harness water from the Kipchorian River to serve domestic, agricultural, and energy needs across the South Rift region.
The project sits at approximately 2,325 meters above sea level, in a region characterized by volcanic geology, highland forest, and significant seasonal rainfall. The dam site borders Londiani Forest and lies within the broader Mau Forest ecosystem — Kenya's largest water tower.
The project is being developed under the Kenya Water Security Programme, with the Environmental and Social Impact Assessment (ESIA) completed and approved by NEMA. Construction is expected to commence in 2026, with excavation and earthworks forming the critical first phase.
KEY PROJECT STATISTICS
- Location: Londiani, Kipkelion East Constituency, Kericho County
- Elevation: 2,325m above sea level
- Catchment: Kipchorian River, Mau Forest ecosystem
- Service Area: Kipkelion East and West, parts of Kericho and Nakuru
- Primary Purpose: Water supply, irrigation, and hydropower
- ESIA Status: Approved by NEMA
- Construction Start: 2026 (anticipated)
DAM COMPONENTS AND EXCAVATION SCOPE
The Londiani Dam project comprises four major components, each requiring significant excavation and earthworks:
1. DAM EMBANKMENT
The main dam structure is an earthfill or rockfill embankment designed to impound water from the Kipchorian River. Excavation scope includes:
- Foundation excavation and preparation across the dam footprint
- Cut-off trench excavation to bedrock for seepage control
- Spoil removal and disposal from foundation zones
- Material sourcing from designated borrow areas for embankment fill
- Compaction and quality control of foundation layers
The volcanic geology of the region means contractors will encounter weathered rock and potentially hard rock formations during foundation excavation. Geotechnical investigations have identified the need for comprehensive ground treatment in some sections.
2. SPILLWAY
The spillway is a critical safety feature designed to release excess floodwater. Excavation scope includes:
- Spillway channel excavation through natural ground
- Energy dissipation basin excavation
- Concrete foundation preparation for spillway structures
- Rock stabilization and slope protection works
3. INTAKE TOWER
The intake tower controls water withdrawal from the reservoir. Excavation scope includes:
- Tower foundation excavation to stable bearing strata
- Access road earthworks
- Platform preparation for tower construction
- Underground conduit excavation if applicable
4. DIVERSION CULVERTS
During construction, river flow must be diverted around the works. Excavation scope includes:
- Diversion channel excavation
- Culvert foundation trenches
- Cofferdam construction and removal
- Streambed restoration post-construction
WATER TREATMENT WORKS AND EARTHWORKS
The Londiani Dam project includes a water treatment plant to process raw water before distribution. The treatment works require:
- Site clearing and bulk excavation for treatment plant foundations
- Excavation for sedimentation tanks, filtration units, and clear water reservoirs
- Earthworks for access roads and utility corridors
- Drainage and stormwater management excavation
- Backfilling and compaction around completed structures
The treatment works site requires careful environmental management due to proximity to the Kipchorian River. Sediment control during excavation is mandatory to prevent water quality degradation downstream.
TRANSMISSION PIPELINE: 50+ KILOMETERS OF EARTHWORKS
The water transmission system is one of the largest earthworks components of the Londiani Dam project. Two gravity mains will distribute treated water across the service area:
| GRAVITY MAIN | ROUTE | EARTHWORKS SCOPE |
|---|---|---|
| Gravity Main 1 | Masaita Tank → Londiani → Kedowa → Chepseon | Trench excavation, pipe bedding, backfilling, road crossings, river crossings |
| Gravity Main 2 | Treatment Works → Kipkelion → Fort Ternan | Trench excavation, pipe bedding, backfilling, road crossings, terrain grading |
Pipeline earthworks include:
- Right-of-way clearing and topsoil stripping
- Trench excavation (typically 1.5–3 meters deep, 0.6–1.2 meters wide)
- Pipe bedding preparation with selected granular material
- Backfilling and compaction in layers
- Road and utility crossing excavations (box culverts, thrust boring)
- River and stream crossing works (cofferdams, fluming)
- Valve chamber and break pressure tank excavations
- Reinstatement of disturbed land and access roads
PIPELINE CHALLENGE: TERRAIN AND GEOLOGY
The pipeline routes traverse highland terrain with volcanic soils, weathered rock, and steep slopes. Contractors must manage:
- High water table sections requiring dewatering
- Rock excavation in volcanic formations
- Steep slope stabilization and benching
- Seasonal flooding during rainy seasons
- Environmental sensitivity in forest and agricultural zones
STORAGE TANKS AND DISTRIBUTION INFRASTRUCTURE
The project includes multiple treated water storage tanks and distribution points:
- Masaita Tank: Primary storage reservoir serving Gravity Main 1
- Kipkelion Storage: Secondary storage for Gravity Main 2
- Distribution Kiosks: Community water points across the service area
Each storage facility requires:
- Site clearing and bulk excavation for tank foundations
- Earthworks for access roads and drainage
- Excavation for inlet and outlet pipe connections
- Platform grading for tank installation
- Surrounding area landscaping and erosion control
ENVIRONMENTAL AND SOCIAL CONSIDERATIONS FOR EXCAVATION CONTRACTORS
The Londiani Dam ESIA identifies several environmental impacts associated with excavation and earthworks. Contractors must implement mitigation measures as a condition of project approval:
SEDIMENT CONTROL
Massive earthworks will generate sediment that can mobilize into the Kipchorian River downstream. Required measures include:
- Silt fences and sediment traps at all excavation discharge points
- Stabilized construction access roads to minimize dust and erosion
- Scheduled earthworks during dry seasons where possible
- Immediate re-vegetation of disturbed slopes
AIR QUALITY MANAGEMENT
Construction equipment, rock crushing, and earthworks generate dust and emissions. Contractors must comply with Kenya's National Air Quality Standards:
- Particulate matter (PM): 50 µg/m³ annual average at property boundary
- Water suppression on haul roads and stockpiles
- Equipment maintenance to minimize exhaust emissions
NOISE AND VIBRATION
Blasting for rock excavation (if required) must comply with occupational and community noise limits. Vibration monitoring is mandatory within 100 meters of structures.
SOCIAL SAFEGUARDS
The project area includes community land, agricultural plots, and cultural sites (including proximity to Mount Londiani / Tulwap-Kipsigis heritage site). Contractors must:
- Respect community access rights during construction
- Compensate for any crop or property damage
- Prioritize local employment and procurement
- Coordinate with community leaders on construction schedules
EQUIPMENT AND CAPACITY REQUIREMENTS FOR LONDIANI DAM EARTHWORKS
A project of this scale requires significant equipment and contractor capacity. Firms bidding for excavation and earthworks packages must demonstrate:
| EQUIPMENT CATEGORY | MINIMUM REQUIREMENT | PURPOSE |
|---|---|---|
| Excavators (30-ton class) | 4–6 units | Dam foundation, spillway, trenching |
| Excavators (20-ton class) | 3–5 units | Pipeline trenches, treatment works |
| Bulldozers (D6–D8) | 4–6 units | Site clearing, grading, embankment works |
| Dump Trucks (30-ton) | 15–25 units | Spoil haulage, material transport |
| Motor Graders | 2–3 units | Haul road maintenance, pipeline grading |
| Compactors (Vibratory) | 3–5 units | Embankment compaction, backfill |
| Hydraulic Breakers | 2–4 units | Rock breaking in volcanic formations |
| Drilling Rigs | 1–2 units | Blast hole drilling (if required) |
| Dewatering Pumps | Multiple sets | Groundwater control in trenches |
CONTRACTOR QUALIFICATION REQUIREMENTS
- NCA Registration: Roads & Civil Works category, minimum NCA 5 for main dam; NCA 4–6 for pipeline packages
- Experience: Minimum 3 similar dam or water infrastructure projects completed
- Financial Capacity: Audited turnover exceeding KSh 500M for main packages
- Technical Staff: Registered engineers, geotechnical specialists, and certified equipment operators
- Insurance: Professional indemnity, contractor's all-risk, and third-party liability
- Environmental Compliance: NEMA-certified environmental management plan
TIMELINE AND CONSTRUCTION PHASES
The Londiani Dam construction is anticipated to follow this phased approach:
| PHASE | DURATION | KEY ACTIVITIES |
|---|---|---|
| Phase 1: Mobilization | 3–6 months | Site establishment, access roads, camp construction, material sourcing |
| Phase 2: River Diversion | 6–9 months | Diversion channel excavation, cofferdam construction, culvert installation |
| Phase 3: Dam Foundation | 12–18 months | Foundation excavation, cut-off trench, ground treatment, embankment construction |
| Phase 4: Spillway & Intake | 12–15 months | Spillway excavation, intake tower foundation, structure construction |
| Phase 5: Treatment Works | 12–18 months | Site earthworks, foundation excavation, structure construction |
| Phase 6: Pipeline | 18–24 months | Right-of-way clearing, trenching, pipe laying, backfilling, testing |
| Phase 7: Commissioning | 6–9 months | Testing, training, handover, site restoration |
| TOTAL PROJECT DURATION | 4–5 years | From mobilization to full commissioning |
OPPORTUNITIES FOR LOCAL AND NATIONAL CONTRACTORS
Londiani Dam presents multiple entry points for contractors of varying capacities:
- Main Dam Earthworks (NCA 3–5): Foundation excavation, embankment construction, spillway — requires large fleet and significant experience
- Pipeline Packages (NCA 4–6): Trenching, backfilling, river crossings — can be split into geographic sections for smaller contractors
- Treatment Works (NCA 5–6): Bulk excavation, foundation preparation, drainage — suitable for medium-sized firms
- Access Roads (NCA 5–7): Haul road construction and maintenance — entry-level opportunity for smaller contractors
- Material Supply: Borrow area operation, aggregate crushing, concrete supply — requires mining/environmental permits
- Subcontracting: Main contractors will subcontract specialized works (blasting, dewatering, geotechnical monitoring)
HOW TO POSITION FOR LONDIANI DAM CONTRACTS
- Ensure NCA registration is current and at the appropriate class
- Register with the procuring entity (county government or national water agency)
- Pre-qualify early — major projects require pre-qualification before tender invitation
- Build relationships with JV partners if your capacity is limited
- Demonstrate environmental compliance capability — NEMA approval is critical
- Invest in equipment or secure hire agreements before bidding
THE BOTTOM LINE: LONDIANI DAM IS A DEFINING PROJECT FOR KERICHO AND THE SOUTH RIFT
The Londiani Dam project represents more than infrastructure — it is water security for Kipkelion, economic opportunity for Kericho County, and a benchmark for Kenya's water sector. For excavation and earthworks contractors, it offers 4–5 years of sustained work across multiple packages, from dam foundation to pipeline distribution.
Success on Londiani Dam requires more than equipment. It demands NCA compliance, environmental stewardship, community engagement, and technical excellence. The contractors who deliver quality earthworks on time and within environmental limits will build reputations that open doors to Kenya's next generation of water projects — from the LAPSSET corridor to the Northern Collector Tunnel Phase 2.
At Trust Partners Geo-Group Ltd, we bring proven dam excavation experience, a modern equipment fleet, and full regulatory compliance to every project. We are registered and ready to partner on Londiani Dam and Kenya's water infrastructure pipeline.
— TRUST PARTNERS GEO-GROUP LTD
READY TO BID FOR LONDIANI DAM OR NEED DAM EXCAVATION EXPERTISE?
Trust Partners Geo-Group is a fully NCA-registered contractor with experience in dam excavation, bulk earthworks, and water infrastructure. Contact us for partnership inquiries, JV opportunities, equipment hire, or project execution across Kenya's water sector.
CALL +254 718 68 69 67 EMAIL US VISIT OUR WEBSITE
NAIROBI HQ | SERVING MOMBASA, KISUMU, NAKURU, ELDORET, THIKA & NATIONWIDE
MON - SAT: 8:00 AM - 6:00 PM | 24/7 EMERGENCY SUPPORT
RELATED RESOURCES
- DAM & WATER PAN EXCAVATION — Irrigation reservoirs, earthfill dams, and flood control
- ROCK EXCAVATION COST IN KENYA 2026 — Complete price guide for hard rock, medium rock, and blasting
- HEAVY EQUIPMENT FOR HIRE — Excavators, bulldozers, dump trucks, graders & more
- NCA CONTRACTOR REGISTRATION — How to register legally and win tenders
- EARTHWORKS COST PER M³ — 2026 rate breakdown for cut and fill, bulk earthworks
TRUST PARTNERS GEO-GROUP LTD | YOUR VISION, OUR EXCAVATION
WEBSITE: WWW.TRUSTPARTNERGEOGROUPLTD.ORG | EMAIL: INFO@TRUSTPARTNERGEOGROUPLTD.ORG | PHONE: +254 718 68 69 67
FOLLOW US: FACEBOOK | TIKTOK | INSTAGRAM | YOUTUBE | LINKEDIN
© 2026 TRUST PARTNERS GEO-GROUP LTD. ALL RIGHTS RESERVED.
LONDIANI DAM CONSTRUCTION 2026: EXCAVATION AND EARTHWORKS SCOPE
INSIDE KERICHO COUNTY'S FLAGSHIP WATER PROJECT — FROM DAM EMBANKMENT TO TRANSMISSION PIPELINES
PROJECT OVERVIEW: WHAT IS LONDIANI DAM?
Londiani Dam is a proposed multi-purpose water storage and supply project in Kericho County, Kenya. Situated near Londiani town in the Kipkelion East Constituency, the dam will harness water from the Kipchorian River to serve domestic, agricultural, and energy needs across the South Rift region.
The project sits at approximately 2,325 meters above sea level, in a region characterized by volcanic geology, highland forest, and significant seasonal rainfall. The dam site borders Londiani Forest and lies within the broader Mau Forest ecosystem — Kenya's largest water tower.
The project is being developed under the Kenya Water Security Programme, with the Environmental and Social Impact Assessment (ESIA) completed and approved by NEMA. Construction is expected to commence in 2026, with excavation and earthworks forming the critical first phase.
KEY PROJECT STATISTICS
- Location: Londiani, Kipkelion East Constituency, Kericho County
- Elevation: 2,325m above sea level
- Catchment: Kipchorian River, Mau Forest ecosystem
- Service Area: Kipkelion East and West, parts of Kericho and Nakuru
- Primary Purpose: Water supply, irrigation, and hydropower
- ESIA Status: Approved by NEMA
- Construction Start: 2026 (anticipated)
DAM COMPONENTS AND EXCAVATION SCOPE
The Londiani Dam project comprises four major components, each requiring significant excavation and earthworks:
1. DAM EMBANKMENT
The main dam structure is an earthfill or rockfill embankment designed to impound water from the Kipchorian River. Excavation scope includes:
- Foundation excavation and preparation across the dam footprint
- Cut-off trench excavation to bedrock for seepage control
- Spoil removal and disposal from foundation zones
- Material sourcing from designated borrow areas for embankment fill
- Compaction and quality control of foundation layers
The volcanic geology of the region means contractors will encounter weathered rock and potentially hard rock formations during foundation excavation. Geotechnical investigations have identified the need for comprehensive ground treatment in some sections.
2. SPILLWAY
The spillway is a critical safety feature designed to release excess floodwater. Excavation scope includes:
- Spillway channel excavation through natural ground
- Energy dissipation basin excavation
- Concrete foundation preparation for spillway structures
- Rock stabilization and slope protection works
3. INTAKE TOWER
The intake tower controls water withdrawal from the reservoir. Excavation scope includes:
- Tower foundation excavation to stable bearing strata
- Access road earthworks
- Platform preparation for tower construction
- Underground conduit excavation if applicable
4. DIVERSION CULVERTS
During construction, river flow must be diverted around the works. Excavation scope includes:
- Diversion channel excavation
- Culvert foundation trenches
- Cofferdam construction and removal
- Streambed restoration post-construction
WATER TREATMENT WORKS AND EARTHWORKS
The Londiani Dam project includes a water treatment plant to process raw water before distribution. The treatment works require:
- Site clearing and bulk excavation for treatment plant foundations
- Excavation for sedimentation tanks, filtration units, and clear water reservoirs
- Earthworks for access roads and utility corridors
- Drainage and stormwater management excavation
- Backfilling and compaction around completed structures
The treatment works site requires careful environmental management due to proximity to the Kipchorian River. Sediment control during excavation is mandatory to prevent water quality degradation downstream.
TRANSMISSION PIPELINE: 50+ KILOMETERS OF EARTHWORKS
The water transmission system is one of the largest earthworks components of the Londiani Dam project. Two gravity mains will distribute treated water across the service area:
| GRAVITY MAIN | ROUTE | EARTHWORKS SCOPE |
|---|---|---|
| Gravity Main 1 | Masaita Tank → Londiani → Kedowa → Chepseon | Trench excavation, pipe bedding, backfilling, road crossings, river crossings |
| Gravity Main 2 | Treatment Works → Kipkelion → Fort Ternan | Trench excavation, pipe bedding, backfilling, road crossings, terrain grading |
Pipeline earthworks include:
- Right-of-way clearing and topsoil stripping
- Trench excavation (typically 1.5–3 meters deep, 0.6–1.2 meters wide)
- Pipe bedding preparation with selected granular material
- Backfilling and compaction in layers
- Road and utility crossing excavations (box culverts, thrust boring)
- River and stream crossing works (cofferdams, fluming)
- Valve chamber and break pressure tank excavations
- Reinstatement of disturbed land and access roads
PIPELINE CHALLENGE: TERRAIN AND GEOLOGY
The pipeline routes traverse highland terrain with volcanic soils, weathered rock, and steep slopes. Contractors must manage:
- High water table sections requiring dewatering
- Rock excavation in volcanic formations
- Steep slope stabilization and benching
- Seasonal flooding during rainy seasons
- Environmental sensitivity in forest and agricultural zones
STORAGE TANKS AND DISTRIBUTION INFRASTRUCTURE
The project includes multiple treated water storage tanks and distribution points:
- Masaita Tank: Primary storage reservoir serving Gravity Main 1
- Kipkelion Storage: Secondary storage for Gravity Main 2
- Distribution Kiosks: Community water points across the service area
Each storage facility requires:
- Site clearing and bulk excavation for tank foundations
- Earthworks for access roads and drainage
- Excavation for inlet and outlet pipe connections
- Platform grading for tank installation
- Surrounding area landscaping and erosion control
ENVIRONMENTAL AND SOCIAL CONSIDERATIONS FOR EXCAVATION CONTRACTORS
The Londiani Dam ESIA identifies several environmental impacts associated with excavation and earthworks. Contractors must implement mitigation measures as a condition of project approval:
SEDIMENT CONTROL
Massive earthworks will generate sediment that can mobilize into the Kipchorian River downstream. Required measures include:
- Silt fences and sediment traps at all excavation discharge points
- Stabilized construction access roads to minimize dust and erosion
- Scheduled earthworks during dry seasons where possible
- Immediate re-vegetation of disturbed slopes
AIR QUALITY MANAGEMENT
Construction equipment, rock crushing, and earthworks generate dust and emissions. Contractors must comply with Kenya's National Air Quality Standards:
- Particulate matter (PM): 50 µg/m³ annual average at property boundary
- Water suppression on haul roads and stockpiles
- Equipment maintenance to minimize exhaust emissions
NOISE AND VIBRATION
Blasting for rock excavation (if required) must comply with occupational and community noise limits. Vibration monitoring is mandatory within 100 meters of structures.
SOCIAL SAFEGUARDS
The project area includes community land, agricultural plots, and cultural sites (including proximity to Mount Londiani / Tulwap-Kipsigis heritage site). Contractors must:
- Respect community access rights during construction
- Compensate for any crop or property damage
- Prioritize local employment and procurement
- Coordinate with community leaders on construction schedules
EQUIPMENT AND CAPACITY REQUIREMENTS FOR LONDIANI DAM EARTHWORKS
A project of this scale requires significant equipment and contractor capacity. Firms bidding for excavation and earthworks packages must demonstrate:
| EQUIPMENT CATEGORY | MINIMUM REQUIREMENT | PURPOSE |
|---|---|---|
| Excavators (30-ton class) | 4–6 units | Dam foundation, spillway, trenching |
| Excavators (20-ton class) | 3–5 units | Pipeline trenches, treatment works |
| Bulldozers (D6–D8) | 4–6 units | Site clearing, grading, embankment works |
| Dump Trucks (30-ton) | 15–25 units | Spoil haulage, material transport |
| Motor Graders | 2–3 units | Haul road maintenance, pipeline grading |
| Compactors (Vibratory) | 3–5 units | Embankment compaction, backfill |
| Hydraulic Breakers | 2–4 units | Rock breaking in volcanic formations |
| Drilling Rigs | 1–2 units | Blast hole drilling (if required) |
| Dewatering Pumps | Multiple sets | Groundwater control in trenches |
CONTRACTOR QUALIFICATION REQUIREMENTS
- NCA Registration: Roads & Civil Works category, minimum NCA 5 for main dam; NCA 4–6 for pipeline packages
- Experience: Minimum 3 similar dam or water infrastructure projects completed
- Financial Capacity: Audited turnover exceeding KSh 500M for main packages
- Technical Staff: Registered engineers, geotechnical specialists, and certified equipment operators
- Insurance: Professional indemnity, contractor's all-risk, and third-party liability
- Environmental Compliance: NEMA-certified environmental management plan
TIMELINE AND CONSTRUCTION PHASES
The Londiani Dam construction is anticipated to follow this phased approach:
| PHASE | DURATION | KEY ACTIVITIES |
|---|---|---|
| Phase 1: Mobilization | 3–6 months | Site establishment, access roads, camp construction, material sourcing |
| Phase 2: River Diversion | 6–9 months | Diversion channel excavation, cofferdam construction, culvert installation |
| Phase 3: Dam Foundation | 12–18 months | Foundation excavation, cut-off trench, ground treatment, embankment construction |
| Phase 4: Spillway & Intake | 12–15 months | Spillway excavation, intake tower foundation, structure construction |
| Phase 5: Treatment Works | 12–18 months | Site earthworks, foundation excavation, structure construction |
| Phase 6: Pipeline | 18–24 months | Right-of-way clearing, trenching, pipe laying, backfilling, testing |
| Phase 7: Commissioning | 6–9 months | Testing, training, handover, site restoration |
| TOTAL PROJECT DURATION | 4–5 years | From mobilization to full commissioning |
OPPORTUNITIES FOR LOCAL AND NATIONAL CONTRACTORS
Londiani Dam presents multiple entry points for contractors of varying capacities:
- Main Dam Earthworks (NCA 3–5): Foundation excavation, embankment construction, spillway — requires large fleet and significant experience
- Pipeline Packages (NCA 4–6): Trenching, backfilling, river crossings — can be split into geographic sections for smaller contractors
- Treatment Works (NCA 5–6): Bulk excavation, foundation preparation, drainage — suitable for medium-sized firms
- Access Roads (NCA 5–7): Haul road construction and maintenance — entry-level opportunity for smaller contractors
- Material Supply: Borrow area operation, aggregate crushing, concrete supply — requires mining/environmental permits
- Subcontracting: Main contractors will subcontract specialized works (blasting, dewatering, geotechnical monitoring)
HOW TO POSITION FOR LONDIANI DAM CONTRACTS
- Ensure NCA registration is current and at the appropriate class
- Register with the procuring entity (county government or national water agency)
- Pre-qualify early — major projects require pre-qualification before tender invitation
- Build relationships with JV partners if your capacity is limited
- Demonstrate environmental compliance capability — NEMA approval is critical
- Invest in equipment or secure hire agreements before bidding
THE BOTTOM LINE: LONDIANI DAM IS A DEFINING PROJECT FOR KERICHO AND THE SOUTH RIFT
The Londiani Dam project represents more than infrastructure — it is water security for Kipkelion, economic opportunity for Kericho County, and a benchmark for Kenya's water sector. For excavation and earthworks contractors, it offers 4–5 years of sustained work across multiple packages, from dam foundation to pipeline distribution.
Success on Londiani Dam requires more than equipment. It demands NCA compliance, environmental stewardship, community engagement, and technical excellence. The contractors who deliver quality earthworks on time and within environmental limits will build reputations that open doors to Kenya's next generation of water projects — from the LAPSSET corridor to the Northern Collector Tunnel Phase 2.
At Trust Partners Geo-Group Ltd, we bring proven dam excavation experience, a modern equipment fleet, and full regulatory compliance to every project. We are registered and ready to partner on Londiani Dam and Kenya's water infrastructure pipeline.
— TRUST PARTNERS GEO-GROUP LTD
READY TO BID FOR LONDIANI DAM OR NEED DAM EXCAVATION EXPERTISE?
Trust Partners Geo-Group is a fully NCA-registered contractor with experience in dam excavation, bulk earthworks, and water infrastructure. Contact us for partnership inquiries, JV opportunities, equipment hire, or project execution across Kenya's water sector.
CALL +254 718 68 69 67 EMAIL US VISIT OUR WEBSITE
NAIROBI HQ | SERVING MOMBASA, KISUMU, NAKURU, ELDORET, THIKA & NATIONWIDE
MON - SAT: 8:00 AM - 6:00 PM | 24/7 EMERGENCY SUPPORT
RELATED RESOURCES
- DAM & WATER PAN EXCAVATION — Irrigation reservoirs, earthfill dams, and flood control
- ROCK EXCAVATION COST IN KENYA 2026 — Complete price guide for hard rock, medium rock, and blasting
- HEAVY EQUIPMENT FOR HIRE — Excavators, bulldozers, dump trucks, graders & more
- NCA CONTRACTOR REGISTRATION — How to register legally and win tenders
- EARTHWORKS COST PER M³ — 2026 rate breakdown for cut and fill, bulk earthworks
TRUST PARTNERS GEO-GROUP LTD | YOUR VISION, OUR EXCAVATION
WEBSITE: WWW.TRUSTPARTNERGEOGROUPLTD.ORG | EMAIL: INFO@TRUSTPARTNERGEOGROUPLTD.ORG | PHONE: +254 718 68 69 67
FOLLOW US: FACEBOOK | TIKTOK | INSTAGRAM | YOUTUBE | LINKEDIN
© 2026 TRUST PARTNERS GEO-GROUP LTD. ALL RIGHTS RESERVED.